When construction resumes the
following construction activities will occur:
- Between Crystal Ridge Drive and Talismon Drive - existing pavement will be removed, curb and gutter will be installed, and asphalt base will be placed.
- The Northwest corner of IL Route 176 and Walkup Road - final grading for the multi-use path and for the sidewalk will begin.
- North and South Sections - the final asphalt placement will take place followed by permanent pavement markings.
- IL Route 176 and Walkup Road – traffic signal installation and activation.
We estimate that the project will be
completed by the end of June, 2013.