Construction activities have been
suspended for the winter and will resume once weather conditions permit.
We estimate that start-up will be approximately mid-April.
When construction resumes the
following construction activities will occur: Between Crystal Ridge Drive and
Talismon Drive - existing pavement will be removed, curb and gutter will be
installed, and asphalt base will be placed.
The Northwest corner of IL Route 176
and Walkup Road - final grading for the multi-use path and for the sidewalk
will begin.
North and South Sections - the
final asphalt placement will take place followed by permanent pavement
markings.
IL Route 176 and Walkup Road – traffic
signal installation and activation.
Mason Hill Road and Crystal Lake Road
– traffic signal installation and activation.
We estimate that the project will be
completed by the end of June, 2013.
No comments:
Post a Comment