Tuesday, July 10, 2012

Walkup Road Work Progress

Consulting Engineers for the project, Baxter and Woodman report:

South section:
Temporary roadway widening for maintenance of traffic on the north side of IL Rte 176 and the west side of Walkup Rd is complete.

A new lane configuration will be in effect on IL Rte. 176 at Walkup starting Wednesday 7/11. Use Caution.


This week, temporary pavement widening continues on Walkup north of Crystal Ridge. Storm sewer work continues on the south leg of Walkup (the section currently closed to traffic).


North section:

Utility relocation work is complete and grading for pavement widening resumed Monday, July 9th on the north section of the project