Final surface course placement (paving) has begun on
IL Route 176 and will take 2 days to complete. Traffic is reduced to a
single lane with flaggers controlling the work zone, so please proceed with
caution.
- Paving on Walkup Road will occur after the completion of paving on IL Route 176. Walkup Road paving will take 2 days to complete once it is started.
- Flashing beacons have been installed on Walkup Road North of Veteran Acres Park for the multi-use path crossing and on Walkup Road just north of Talismon Drive for a pedestrian crossing. The beacons are not yet active. They will be activated on June 5th.
- Manhole final adjustments are complete. Use caution while driving through the area as construction barrels are still present on some manholes
- .Curb and gutter installation along IL Route 176 and Walkup Road is complete.
- Final sidewalk placement and landscaping along IL Route 176 and Walkup Road will begin once paving is complete.
- The temporary traffic signal at IL Route 176 and Walkup Road will be deactivated and the newly installed permanent traffic signal will be activated on June 6th.
North Section
- Pavement striping has started today and should take 1 day to complete. Please be aware of workers and use caution when traveling through this area.
- The new traffic signal installed at Mason Hill Road and Crystal Lake Road is scheduled to be activated on June 6th.
- Work is nearing completion, but both sections are still considered construction work zones. Traffic control may be required at times so please slow down and proceed with caution.