Asphalt
binder course placement is complete on the west side of Walkup Road from north
of Talismon Drive to south of Crystal Ridge Drive. Final surface course will be
installed within the next several weeks.
·
Installation
of the concrete handholes in the left turn lanes for signal wiring is complete.
Mast arms (traffic signal poles) are currently being installed. Temporary
pavement markings have been placed to help guide you through the intersection,
please drive carefully and watch for intermittent lane closures at the
intersection to facilitate signal pole installation.
·
Manhole
final adjustments will occur next week. Use caution while driving through
the area as construction barrels will be placed on some manholes that you will
need to avoid while the concrete used for adjustments is curing.
·
The
temporary traffic signal at IL Route 176 and Walkup Road will be deactivated
and the newly installed permanent traffic signal will be activated on June 6th.
·
Multi-use
path installation is complete along the east side of Walkup Road.
·
Sidewalk
installation along IL Route 176 and Walkup Road is ongoing.
·
Landscaping
will start next week.
North Section:
·
Paving
of the final lift of asphalt is scheduled to be completed today.
·
Shoulder
stone will be placed next week.
·
Permanent
pavement striping is scheduled to occur next week.
·
Please
be aware: the new traffic signal installed at Mason Hill Road and Crystal Lake
Road is scheduled to be activated June 6th.
·
Temporary
lane closures and flagger operations may be required at times so please slow
down and proceed with caution.