Friday, November 2, 2012

Walkup Road Work Continues

 North Leg: The storm sewer installation will be complete early next week, earth excavation work is being completed, and stone placement for the remaining widening will continue next week.

Landscaping of the east side is complete and west side (south end) is complete.  Daily lane closures will continue.


South Leg
: Storm sewer work will resume next week now that pavement removal is complete.  The retaining wall along IL Route 176 is complete and will be backfilled to allow remaining storm sewer installation and completion of roadway construction on IL Route 176.  

Asphalt is currently being placed along IL 176 and to the immediate north on Walkup.


Driveway placement along IL 176 should be completed next week.  Expect a new traffic pattern on Walkup immediately north of IL 176 within the next couple of weeks.