North Leg:
Curb installation has been completed
and backfilling has started. Asphalt widening placement will start next
week, followed by pavement profile grinding to level the surface in
anticipation of binder placement across the entire roadway shortly after Thanksgiving.
Landscape restoration will follow the asphalt work.
South Leg:
Storm sewer work continues on IL Rte
176 and Walkup at the Northwest corner. Fine grading and stone base placement
from Burning Bush Trail to Talismon Drive has started. Curb placement is
scheduled for next week. Curb placement will be followed by asphalt
placement. The wall along Veteran Acres is proceeding w/ the concrete
facing being placed.
Please be alert and watch for workers and equipment