Smaller intersection pours will also be done. The concrete needs to be sawcut shortly after it is placed to control cracking. It may be necessary for some of these sawcuts to be done after normal working hours. To the extent possible, efforts will be made to minimize the noise disruption.
The bicycle path will continue to be closed at the south side of Rakow to allow some of these concrete pours to be completed. It will be reopened by the end of the day on Friday, September 16th.
Expect traffic delays along the project as this work is done. Flaggers will be used for these pours so please be alert!
Thank you for your continued patience.
No comments:
Post a Comment