Traffic has been realigned from the
Veteran Acres Park entrance to IL Rte. 176.
Daily lane closures will
occur on Walkup Road from Talismon Drive to IL Rte. 176 to allow work to resume
on this remaining stretch of Walkup to be completed. Pavement removal on
Walkup Road from Talismon Drive to IL Rte. 176 began 4/4/13 and will be
followed by storm sewer installation approximately 4/9/13.
Remaining work
on Walkup Road includes - the storm sewer installation, stone placement, curb
and gutter completion, and asphalt installation. Curb and gutter and
sidewalk installation should also begin on IL Rte. 176 starting within 2 weeks.
Watch for traffic flaggers, avoid using your cell phone and drive safely
through the construction zone.