North Leg:
On Wednesday afternoon, primecoat
(oil) was placed on Crystal Lake Avenue from Anvil Road to the north end of the
project in preparation for Hot Mix Asphalt (HMA) placement that began Thursday
11/29. Hot Mix Asphalt placement will continue for the next several
days. Pavement striping for the winter will follow once HMA placement is
complete. Final landscape restoration will be completed following the
asphalt placement.
South Leg:
Work will continue on the retaining
wall along Walkup Road by Veteran Acres with completion scheduled for late next
week. Curb was placed Thursday 11/29 along Walkup Road from south of
Crystal Ridge Drive and on IL Route 176 west of the Walkup Road/IL Route 176
intersection. Paving of this area will begin early next week. Also
next week, paving will occur on the southbound lanes of Walkup Road from
Talismon Drive to Burning Bush Trail.