Early this coming week, traffic will be shifted to the newly placed asphalt lane.
Topsoil, seed, and erosion blanket placement has begun in the right-of-way.
Earth excavation has begun in South Section
South Section Walkup Road ---
On Illinois Route 176, stone base placement has begun
in preparation for curb installation. Work continues on the retaining wall in
front of the shopping complex west of Walkup on Route 176.
On Walkup Road, stone base placement has begun in preparation for asphalt placement next week.
On Walkup Road, stone base placement has begun in preparation for asphalt placement next week.
No comments:
Post a Comment