North Leg:
The final landscaping is complete and additional erosion control measures are in place for the winter snow.  The temporary striping is almost complete.  The lane lines are in place but some additional markings at turn lanes and shoulders are expected to be complete any day (weather permitting).  Once striping is complete, the work zone speed limit will be removed and final signage will be placed. 

South Leg:
The final landscaping is ongoing.  Some areas where work remains will see temporary stabilization in place for the winter.  The electrical contractor is working on new traffic signal foundations at the intersection of Walkup/IL 176.  Temporary striping is nearing completion