Wednesday, November 28, 2012

Walkup Road Work Continues

North Leg: 
Profile grinding to level the pavement will be completed Wednesday 11/28 in the morning.  On Wednesday afternoon, primecoat (oil) will be placed on Crystal Lake Avenue from Anvil Road to the north end of the project in preparation for Hot Mix Asphalt (HMA) placement that is scheduled to begin Thursday 11/29.  Pavement striping for the winter will follow once HMA placement is complete.  Final landscape restoration will be completed following the asphalt placement.

South Leg:
Work will continue on the retaining wall along Walkup Road by Veteran Acres with completion scheduled for late next week.  Curb placement is scheduled for Thursday 11/29 along Walkup Road from south of Crystal Ridge Drive and on IL Route 176 west of the Walkup Road/IL Route 176 intersection.  Paving of this area will begin late next week.  Also next week, paving will occur on the southbound lanes of Walkup Road from Talismon Drive to Burning Bush Trail. 

No comments: