North Leg:
On Wednesday afternoon, primecoat (oil) was placed on Crystal Lake Avenue from Anvil Road to the north end of the project in preparation for Hot Mix Asphalt (HMA) placement that began Thursday 11/29.  Hot Mix Asphalt placement will continue for the next several days.  Pavement striping for the winter will follow once HMA placement is complete.  Final landscape restoration will be completed following the asphalt placement.

South Leg:
Work will continue on the retaining wall along Walkup Road by Veteran Acres with completion scheduled for late next week.  Curb was placed Thursday 11/29 along Walkup Road from south of Crystal Ridge Drive and on IL Route 176 west of the Walkup Road/IL Route 176 intersection.  Paving of this area will begin early next week.  Also next week, paving will occur on the southbound lanes of Walkup Road from Talismon Drive to Burning Bush Trail.