Walkup Road Work Moving Along

South section-
Pavement removal and earth excavation will continue on the north side of IL Route 176 and on Walkup between Park View and Talismon Drive. New curb and gutter will be installed next week in these areas.

Work continues on the new retaining wall along Veteran Acres, and work will start on the retaining wall along the shopping mall located on IL 176.

North section-
Curb and gutter installation will be completed early next week on the east side of Walkup. Stone grading and asphalt widening will follow. Traffic lane shifting may occur at the end of next week – watch for updates.

Please proceed with caution through the work zones – construction personnel and equipment will be present. Expect delays as the work scheduled will impact traffic.