Area Road Work Update

Curb installation on Walkup Road is complete and will be followed next week by asphalt placement, final striping, landscaping, and multi-use path construction.
Project work on IL Route 176 for the next week will consist of the grading of the area behind the curb, continued sidewalk installation and asphalt placement.
Traffic signal installation continues on IL Route 176 and Walkup Road.
North Section:
Traffic signal installation at Mason Hill Road is ongoing, but the signal will not be turned on for use until surfacing is complete and the final striping configuration is in place.
The remaining work on the North Section is final surfacing, striping, traffic signal installation at Mason Hill Road, and punch list cleanup.  Paving is expected to begin within the next two weeks and will take approximately one to two weeks to complete.