Friday, March 1, 2013

Walkup Avenue Construction Suspended For Winter

Construction activities have been suspended for the winter and will resume once weather conditions permit.  We estimate that start-up will be approximately mid-April. 

When construction resumes the following construction activities will occur:
  • Between Crystal Ridge Drive and Talismon Drive - existing pavement will be removed, curb and gutter will be installed, and asphalt base will be placed.
  • The Northwest corner of IL Route 176 and Walkup Road - final grading for the multi-use path and for the sidewalk will begin.
  • North and South Sections - the final asphalt placement will take place followed by permanent pavement markings.
  • IL Route 176 and Walkup Road – traffic signal installation and activation.

We estimate that the project will be completed by the end of June, 2013.