Thursday, October 4, 2012

Walkup Avenue Work Continues

North Section:
Concrete curb will be placed Friday 10/5 in the southbound direction from north of Coach Light Road to Anvil Road.

Also, asphalt placement will begin northbound on Friday 10/5 from north of Coach Light Road to Patriot Estates (Cunat Drive) and will continue into Monday 10/8.


Intermittent lane closures are necessary for this work, so using alternate routes if possible is recommended.


South Section:
Storm sewer installation continues along IL 176. The excavation along IL 176 west of Walkup Road is complete and crews will begin forming the retaining wall.

Grading and stone placement will follow the completion of this work in the next couple of weeks.

The retaining wall adjacent to Veteran Acres remains under construction. The soldier piles being drilled should be completed by mid-next week. The concrete facing will then start to be formed and poured. Asphalt placement from Talismon Drive to Burning Bush Trail should start late next week.

No comments: