South Section: Multiple storm sewer installations are in progress on IL Route 176 and Walkup. Earth excavation and aggregate placement continues on IL Route 176 and Walkup in preparation for curb placement. Wetland cell restoration is complete at Veteran Acres Park.  Frogs and other wildlife seem to be enjoying the restoration!   SEE PHOTOS.

North Section: Storm sewer installation work is continuing. Earth excavation and aggregate placement continues in preparation for curb placement.